A working draft of a road bridge at Km 51 + 845.08 developed in the project of Overhaul works of motor road "M-07 Kyiv–Kovel–Yagodin on Km 30 + 680 – Km 64 + 000" section within Kyiv Oblast.

The project proposes the construction of a bridge over the Zdvizh River.

Technical parameters of the bridge:

  • The layout of a bridge is 32.5 m + 36.0 m + 32.5 m;
  • Bridge size - S = 10.5 + 2 x 1.50 m;
  • The superstructure of the bridge is made of a monolithic prestressed concrete beam;
  • End piers are designed on bored piles foundation D = 1000 mm, and consist of bolt, backwall, wing walls;
  • Intermediate piers are designed on bored piles foundation D = 1000 mm, and consist of a monolithic reinforced concrete massive part and grillage.